Shri Nand Lal Sharma, Chairman & Managing Director SJVN virtually inaugurated the works of the Second Unit of (2 X 660) 1320 MW Buxar Thermal Power Plant. On this occasion Sh. Sushil Kumar Sharma Director (Electrical), SJVN & Sh. Sanjeev Sood CEO, SJVN Thermal Pvt. Ltd (STPL) were also present at Project Site along with other senior officials.
Speaking on the occasion Sh. Nand Lal Sharma informed that the Foundation Stone of 1320 MW Buxar Thermal Power Plant was laid by Hon’ble Prime Minister of India Shri Narendra Modi on 9th March 2019. Sh. Sharma also informed that the progress of the Project is being continuously monitored by Hon’ble Union Minister for Power & NRE, Sh. R. K Singh. He exhorted all stakeholders to enthusiastically strive hard to commission the Project before the scheduled timeframe.
He further stated that the project consists of two units and that more than 50 % of works related to the First unit have already been completed. The 1320 MW Buxar Thermal Power Plant with Ultra Super Critical Technology is being developed by SJVN Thermal Pvt. Ltd (a fully owned subsidiary of SJVN Limited). The Plant involves an investment of around Rupees 11,000 Crore. On commissioning, the plant will generate 9828 Million Units of electricity. He emphasized contributing towards the target of “24X7 Power for All” set by the Hon’ble Prime Minister of India. He stated that every individual associated with activities of the Plant has to concertedly work towards commissioning the first unit of the Plant by June 2023 and the second unit by January 2024.